The Segmental Box Girder (SBG) Casting Yard in Sepang will be able to produce a total of 17,000 SBGs for the construction of the KVMRT’s twin track.
Each of these 11metres-wide SBGs weighs about 45 tonnes. The first delivery of SBGs is expected in January 2013, to be used for the V5 KVMRT
package (from Taman Bukit Ria to Plaza Phoenix, Cheras)
Construction works for KVMRT have commenced, with
significant activities at V1 (sungai Buloh – Kota Damansara),
V4 (seksyen 16 – semantan), V5 (Taman Bukit Ria – Plaza
Phoenix), V6 (Taman suntex – Bandar Tun hussein onn)
and V7 (Balakong - saujana impian). site preparation and
utility relocation works are advancing fast at these sites,
with pier construction works in progress at V4, V5 and V6.
The Centralised labour Quarters at sungai Buloh and Plaza
Phoenix are being completed expeditiously, in time to house
more than 7,000 KVMRT workers by Q2, 2013.
Works for the KVMRT underground package covering seven
underground stations and two portals are proceeding fast.
The redevelopment of Klang Bus station that includes
the demolition of Klang Bus stand, Plaza Warisan and
uo superstore is in progress for the construction of Pasar
seni KVMRT station. underground stations such as Kl
sentral, Merdeka, Pasar Rakyat, Cochrane and Maluri have
advanced into diaphragm wall construction for the station
box. in preparation for the 9.5km tunnel drive in Q2, 2013,
10 tunnel boring machines have been procured.